Jonathon Huse
Mechanical
- Jul 29, 2016
- 4
Hi guys,
On a current project we are installing a new steam line and pressure reducing station to service a crude vegetable oil refining plant. The inlet pressure to the station is 10 barg (boiler pressure), and out of the PRV the pressure is 3 barg i.e. the operating pressure of the refinery/process plant equipment (heat exchangers).
The question I have is primarily around best practice guidelines for the installation of the PRV itself. My understanding to date was to ensure a certain amount of pipe diameters (straight) before and particular after the valve/pressure drop, to ensure laminar flow and accurate modulation. My understanding was to allow 2-4 diameters beforehand, and at least 10 afterwards of straight pipe. On the current Bailey PRV that the contractors have installed, they have left 10 before the valve, but only 4-5 after. After then reading the technical manual for this valve, this is actually the supplier recommendation. My questions I hope you guys can answer:
- Is it not more critical to have laminar flow after the PRV (i.e. minimum 10 pipe diameters) so as to ensure the pressure in the downstream/low pressure port is accurate? And is this not because turbulent flow causing vortices/eddy currents can create points of lower/higher pressure which if reaching the port, provide a false indication of line pressure and cause the valve to oscillate accordingly.
- Similar to the above, with the reduction in pressure and thus increase in velocity (kinetic energy), the pipe immediately on the discharge of the PRV should be 1-2 pipe sizes greater than the inlet size?
- The reason best practice guidelines commonly say only 2 diameters of straight pipe on the inlet is because the inlet pressure is not the critical control parameter compared to the discharge pressure with which the equipment operates?
Would really appreciate some guidance on this. The more detail into the fundamental engineering flow mechanics of it the better as i'm into that level of detail, even as a high level project manager. Have attached a photo of the contractors installation which I questioned during my site visit today.
On a current project we are installing a new steam line and pressure reducing station to service a crude vegetable oil refining plant. The inlet pressure to the station is 10 barg (boiler pressure), and out of the PRV the pressure is 3 barg i.e. the operating pressure of the refinery/process plant equipment (heat exchangers).
The question I have is primarily around best practice guidelines for the installation of the PRV itself. My understanding to date was to ensure a certain amount of pipe diameters (straight) before and particular after the valve/pressure drop, to ensure laminar flow and accurate modulation. My understanding was to allow 2-4 diameters beforehand, and at least 10 afterwards of straight pipe. On the current Bailey PRV that the contractors have installed, they have left 10 before the valve, but only 4-5 after. After then reading the technical manual for this valve, this is actually the supplier recommendation. My questions I hope you guys can answer:
- Is it not more critical to have laminar flow after the PRV (i.e. minimum 10 pipe diameters) so as to ensure the pressure in the downstream/low pressure port is accurate? And is this not because turbulent flow causing vortices/eddy currents can create points of lower/higher pressure which if reaching the port, provide a false indication of line pressure and cause the valve to oscillate accordingly.
- Similar to the above, with the reduction in pressure and thus increase in velocity (kinetic energy), the pipe immediately on the discharge of the PRV should be 1-2 pipe sizes greater than the inlet size?
- The reason best practice guidelines commonly say only 2 diameters of straight pipe on the inlet is because the inlet pressure is not the critical control parameter compared to the discharge pressure with which the equipment operates?
Would really appreciate some guidance on this. The more detail into the fundamental engineering flow mechanics of it the better as i'm into that level of detail, even as a high level project manager. Have attached a photo of the contractors installation which I questioned during my site visit today.