CostasV
Mechanical
- May 29, 2003
- 126
Hi all,
Recectly, it came to our responsibility a natural gas network that has underground concrete chambers (3m X 3m X 3m) as valve stations. In these chambers, there are the gas pipes (main pipe 3m long, 10" diameter, secondary pipe 6m long, 2" diameter) and the valves (of the same diameter). In one of these chambers, we found it full of water. We remove the water and we notice that the paint of the pipe was "wetted" and could be easily removed even with the bare hand, leaving a brown color surface. Any thoughts of what is to be done regarding the pipes? I am thinking of cleaning (removing the old paint) the pipe, drying the chamber, and repainting it. Is it worthy to measure the thickness (by ultra sound)?
Other Data
1. Water inside the chamber must have entered either from the top opening, or from the entrance of the 10" pipe accross the concrete chamber (which is about 2m below the ground level). It is rain water and we estimate that it should be there for about 24 to 30 months.
2. The material of the pipes is API 5L Grade B.
3. According to our specifications, the painting should be in 3 layers, first layer 50 micron thick, second layer 30 micron thick and third layer 160 micron thick. Durability of painting system should be per MIL-P-23236 I/4556 D (Sorry, I don't know what is this).
4. The pipes that are inside the concrete chamber are NOT cathodically protected
I appreciate any recomendations
Costas
Recectly, it came to our responsibility a natural gas network that has underground concrete chambers (3m X 3m X 3m) as valve stations. In these chambers, there are the gas pipes (main pipe 3m long, 10" diameter, secondary pipe 6m long, 2" diameter) and the valves (of the same diameter). In one of these chambers, we found it full of water. We remove the water and we notice that the paint of the pipe was "wetted" and could be easily removed even with the bare hand, leaving a brown color surface. Any thoughts of what is to be done regarding the pipes? I am thinking of cleaning (removing the old paint) the pipe, drying the chamber, and repainting it. Is it worthy to measure the thickness (by ultra sound)?
Other Data
1. Water inside the chamber must have entered either from the top opening, or from the entrance of the 10" pipe accross the concrete chamber (which is about 2m below the ground level). It is rain water and we estimate that it should be there for about 24 to 30 months.
2. The material of the pipes is API 5L Grade B.
3. According to our specifications, the painting should be in 3 layers, first layer 50 micron thick, second layer 30 micron thick and third layer 160 micron thick. Durability of painting system should be per MIL-P-23236 I/4556 D (Sorry, I don't know what is this).
4. The pipes that are inside the concrete chamber are NOT cathodically protected
I appreciate any recomendations
Costas