Can someone help settle a dispute between our staff.
Our Contract is written in vague language. It says: you basically pay for stored materials.
The Contractor has stored $10,000 worth of materials at the site. Now it is time to make the second progress payment.
Pay # 1 - $10,000 Stored Materials & $100,000 Work Total
Total Payment 1 = $110,000
Pay #2 - $5,000 Stored Materials (Remaining has used some up) & $220,000 Work Total
Total Payment 2 = $225,000 - $110,000 (Pay 1) = $110,000
one person says we should force the $5000 to $0 under Pay #2. i dont believe this is fair b/c this would force the contractor to absorb the materials stored. basically we would be breaking the contract since arent paying him for stored materials.
Our Contract is written in vague language. It says: you basically pay for stored materials.
The Contractor has stored $10,000 worth of materials at the site. Now it is time to make the second progress payment.
Pay # 1 - $10,000 Stored Materials & $100,000 Work Total
Total Payment 1 = $110,000
Pay #2 - $5,000 Stored Materials (Remaining has used some up) & $220,000 Work Total
Total Payment 2 = $225,000 - $110,000 (Pay 1) = $110,000
one person says we should force the $5000 to $0 under Pay #2. i dont believe this is fair b/c this would force the contractor to absorb the materials stored. basically we would be breaking the contract since arent paying him for stored materials.