Bala0404
Structural
- Dec 1, 2015
- 20
Till now I am in the design aspect of the projects. today my manager asked me to estimate the structural fee of a three story steel building with cmu shafts and metal deck building with non load bearing cold formed sin.
BUilding is 200 ft x100 ft.
Building construction cost was not provided to me.
I am estimating as below
1. General notes, 3 plans, two foundation, 2 steel, cmu and bracing, 1 typical concrete and 1 typical steel details. All total 12 sheets.
Do we typically give the estimates based on square footage or based on sheets? I an roughly give him a price based on my experience. ( 4 weeks to do the job.w/ $80/hr approx.).
Is this how we do? or do we have to reduce the price to compete with other firms
BUilding is 200 ft x100 ft.
Building construction cost was not provided to me.
I am estimating as below
1. General notes, 3 plans, two foundation, 2 steel, cmu and bracing, 1 typical concrete and 1 typical steel details. All total 12 sheets.
Do we typically give the estimates based on square footage or based on sheets? I an roughly give him a price based on my experience. ( 4 weeks to do the job.w/ $80/hr approx.).
Is this how we do? or do we have to reduce the price to compete with other firms