metzdmichael
Structural
- Mar 1, 2024
- 3
A previous structural steel subcontractor and general contractor fabricated steel on my project. The entire project got delayed by approximately six months and the delivered steel sat outside in the elements during this time. The new steel rusted, and had "above average industry standard" rust on the steel. This was mainly surface rust. When the new general contractor and structural steel subcontractor came on to erect the building, the inspector required all bolted connections be sanded to remove the rust for slip coefficient. My question is, what is the industry standard for allowable rust on beams and columns? I know with the project being delayed for so long and the beams sitting outside in the elements, that is not industry standard for time exposed to elements, what is the industry standard time for steel allowed to be exposed to the elements? Like two weeks? The project teams are arguing on the costs for who should be responsible for the sanding of the bolted connections.