nader666
Structural
- Mar 7, 2013
- 21
Hi everyone,
I have designed a T steel supports for overhead duct line. The contractor have used channels between the T support and the pipe support (photo attached) to make up the difference in elevation due to some short T supports. The contractor did not get a field adjustment approval and did it without bringing the problem to the field inspector. The contractor has agreed to replace some the horizontal I beams but he is trying to claim that some should be accepted because it is normal field adjustment due to allowable survey error and trying to get approval of field adjustment detail (sketch attached)for some of the adjusted supports. My question is how much the reasonable tolerance that could be accepted in such case and if there is any code that limits the tolerance of field adjustment and should be applied in this case.
Thank You
Happy New Year
I have designed a T steel supports for overhead duct line. The contractor have used channels between the T support and the pipe support (photo attached) to make up the difference in elevation due to some short T supports. The contractor did not get a field adjustment approval and did it without bringing the problem to the field inspector. The contractor has agreed to replace some the horizontal I beams but he is trying to claim that some should be accepted because it is normal field adjustment due to allowable survey error and trying to get approval of field adjustment detail (sketch attached)for some of the adjusted supports. My question is how much the reasonable tolerance that could be accepted in such case and if there is any code that limits the tolerance of field adjustment and should be applied in this case.
Thank You
Happy New Year