Reesh14
Electrical
- Aug 3, 2005
- 38
I have a 225A, 120/208V,3ph,4w panel that serves two boilers, two pumps, exhaust fan, receptacles, and other equipment in a boiler room. I want to add a 200A/3P breaker to it to serve a new rooftop unit. Total load is estimated at about 180A for the panel including the RTU. I was told by the panel manufacturer that I would have to replace it with a new panel in order to have a subfeed breaker for the new RTU. The feed for this panel from a MDP is 225A. I was told to replace the panel with a 400A panel rather than a 225A panel and use the same feed breaker from the MDP. The rep. from GE told me that the bus has to be rated for 400A because it was to be higher than the 200A subfeed breaker, but he was not sure. At the same site, there are 225A panels serving RTU's with 200A subfeed breakers along with other equipment which goes against what the rep told me. Is there an article in NEC that involves this? Thanks!