Motto33
Geotechnical
- Aug 9, 2023
- 1
Hi everyone, thanks in advance for your help.
We are inspecting a geogrid-reinforced ecology block wall being constructed. The subgrade soils are loose sands and sandy silt that are generally moist, but are wet right now in some areas due to surface water coming through the site. The surface water impacts about 10% of wall alignment. We excavated 18 inches below grade and placed a 6-inch layer of gravel below the first layer of blocks. However, when we compacted that lift, we saw the subgrade liquefying and pumping.
How concerned should I be about the stability of the wall (which will be 9 feet tall = 4 blocks high, and will have reinforcement)? Once pore pressures subside, will the subgrade be stable enough that pore pressure won't be an issue?
This is a temporary wall that will be used to support a temporary work platform - it will be removed in 4 months. There will be a perforated drain behind the wall.
We are inspecting a geogrid-reinforced ecology block wall being constructed. The subgrade soils are loose sands and sandy silt that are generally moist, but are wet right now in some areas due to surface water coming through the site. The surface water impacts about 10% of wall alignment. We excavated 18 inches below grade and placed a 6-inch layer of gravel below the first layer of blocks. However, when we compacted that lift, we saw the subgrade liquefying and pumping.
How concerned should I be about the stability of the wall (which will be 9 feet tall = 4 blocks high, and will have reinforcement)? Once pore pressures subside, will the subgrade be stable enough that pore pressure won't be an issue?
This is a temporary wall that will be used to support a temporary work platform - it will be removed in 4 months. There will be a perforated drain behind the wall.