Mila2015
Electrical
- Oct 11, 2019
- 28
I used ETAP software to design 44KV substation ground grid. For the shape of my particular substation, I had to use Finite Element Method, and not the IEEE 80. My question is regarding Meth sizes, and conductor spacing. The IEEE 80 design requires that minimum spacing between conductors is 2.5m (I believe NEC requires 6ft). THE FEM used in ETAP doesn't have this requirement. THis is because IEEE 80 requires fixed shapes, while FEM is very flexible and calculates values based on actual design.
Due to the very high soil resistivity values, in order to meet "touch" and "step" potential values, and not have to end up with a very large grid, my spacing between conductors was closer to 5ft. This design met all safety requirement, and client's max resistance value. Anyone sees issue with being under 6ft spacing in this situation? Thanks for the help!
Due to the very high soil resistivity values, in order to meet "touch" and "step" potential values, and not have to end up with a very large grid, my spacing between conductors was closer to 5ft. This design met all safety requirement, and client's max resistance value. Anyone sees issue with being under 6ft spacing in this situation? Thanks for the help!