dachenglee
Civil/Environmental
- Apr 14, 2004
- 10
I am working on a new sanitary sewer construction subsurface investigation plan. The proposed sewer will be 5,000 ft long along existing roads and the inverts will be 10 to 20 ft under the surface. Does any one know how the depths and intervals of borings should be designed? Since the borings and samples are expensive, my idea is to do probes or test pits every 200 ft next to the road. If the tests find refusal above planned depth, then do drilled borings. Please give me your suggestions. Thanks.