I'm looking for recommendations for minimum longitudinal reinforcement for a super-flat floor. I have a requirement of Fmin=65 and am designing the strips for the floor. I have the strip joints located in the middle of the storage racks. The strips are 200 feet long. What is the recommendation for longitudinal reinforcement in the strips to distribute the cracks?
ACI 360.1 section 8.3 states to use p=0.005 for the steel reinforcing. It does not state if this is top reinforcing or total. And it does not state this is for super flat strip pours. I have an 8" slab with a requirement of top & bottom reinforcing by the client. Would the pmin=0.005 be for top bars of #5 at 11" o.c. or T&B #4 @ 10" o.c.? Or should I be looking at another recommendation?
Thanks.
ACI 360.1 section 8.3 states to use p=0.005 for the steel reinforcing. It does not state if this is top reinforcing or total. And it does not state this is for super flat strip pours. I have an 8" slab with a requirement of top & bottom reinforcing by the client. Would the pmin=0.005 be for top bars of #5 at 11" o.c. or T&B #4 @ 10" o.c.? Or should I be looking at another recommendation?
Thanks.