BigH
Geotechnical
- Dec 1, 2002
- 6,012
Quick question: What do most of you do for soaked CBR as far as surcharge is concerned? Do you use the nominal 5 to 10kg or do you actually put on a surcharge equivalent to the pavement structure even though commercially available moulds don't readily handle 30kg+ ??
and Thanks!