RAGE69
Structural
- Sep 21, 2016
- 2
Hi All
I am building an above ground pool sitting on concrete piers founded onto rock(due to slope of the land most of the pool including the base is above the ground).
The engineer has specified N12-200 bars each way on each face.
Trying to get quotes and a pool contractor to build it - all of them complaining that they normally use S12 bars and not N12 bars when constructing pools and that N12 bars make the build too difficult.
I would be of the opinion that the engineer is correct but I have had several pool builders say the same thing.
Is this a case of a conservative engineer or more a case of a contractor wanting to take the easy option instead of doing what is correct
I am building an above ground pool sitting on concrete piers founded onto rock(due to slope of the land most of the pool including the base is above the ground).
The engineer has specified N12-200 bars each way on each face.
Trying to get quotes and a pool contractor to build it - all of them complaining that they normally use S12 bars and not N12 bars when constructing pools and that N12 bars make the build too difficult.
I would be of the opinion that the engineer is correct but I have had several pool builders say the same thing.
Is this a case of a conservative engineer or more a case of a contractor wanting to take the easy option instead of doing what is correct