tumbleweed1
Electrical
- Sep 19, 2013
- 44
Say we have two groups of 2 generators, each group capable of 4000A output. And we connected the load/utility line to the middle of the bus between each group. Can we get away with sizing each generator switchgear bus to 4000A each, and simply have a middle transition cell with 8000A of bussing?
I'm envisioning cell 1 and 2 each with 4000A common bus, cell 3 the transition cell and outgoing with 8000A bus, and cell 4 and 5 with 4000A common bus.
As per Canadian Electrical Code, this seems to suit 14-100.
Would this be a correct way of doing things?
I'm envisioning cell 1 and 2 each with 4000A common bus, cell 3 the transition cell and outgoing with 8000A bus, and cell 4 and 5 with 4000A common bus.
As per Canadian Electrical Code, this seems to suit 14-100.
Would this be a correct way of doing things?