When a typical slab on grade/cmu stem wall foundation (see attached) starts getting higher lets say over 6 ft (exposed face above grade) would you analyze as a cantilever retaining wall? or could you assume you have a pin-pin with the keyed in slab holding back the wall? I often detail dowels in the slab hooked into the top of the chair block an effort to help with any differential settlement but I don't think I these could be adequately(per code) developed into the masonry or 4" thick slab?