AlexWong122
Structural
- Apr 23, 2018
- 28
Hi all,
I recently joined a new company and one of the mandate is to inspect temporary excavation slope stability for house basement construction. Due to the space limitation, I was told that for slope height less than 8', the common practice is to make the temporary cut slope about 1H:7V (on dense silty material)and cover the whole slope with poly liner and call it good for the next 30 days (if it rains heavily then the slope need to be re-inspect). I am a civil engineer and my past experience is usually a temporary cut slope of 1H:1V for soil and 1H:4V for rock. I don't know too much about geotechnical engineering but this is much different than all my previous experience. However as I go around the city (Vancouver, Canada) I do see a lot of sites (maybe 50%) are using this cut slope (i.e. 1H:7V) for soil.
Attached is one of the example.
Can anyone share some knowledge to me with this topic?
Thanks,
Alex
I recently joined a new company and one of the mandate is to inspect temporary excavation slope stability for house basement construction. Due to the space limitation, I was told that for slope height less than 8', the common practice is to make the temporary cut slope about 1H:7V (on dense silty material)and cover the whole slope with poly liner and call it good for the next 30 days (if it rains heavily then the slope need to be re-inspect). I am a civil engineer and my past experience is usually a temporary cut slope of 1H:1V for soil and 1H:4V for rock. I don't know too much about geotechnical engineering but this is much different than all my previous experience. However as I go around the city (Vancouver, Canada) I do see a lot of sites (maybe 50%) are using this cut slope (i.e. 1H:7V) for soil.
Attached is one of the example.
Can anyone share some knowledge to me with this topic?
Thanks,
Alex