JECCNC
Civil/Environmental
- Apr 5, 2003
- 15
I am on a project which uses an induced draft counter flow cooling tower, the system uses sea water and has a basin about 300 meters x 35 meters and 2.5 meter deep, there is also a pump basin which is about 7 meter deep. my question is regarding the testing of this basin for leaks. some codes say 8 hrs, some 24 hrs , 3 days and 21 days. does any one know what these test times are based on? any advice on which to follow