We are currently managing the design build of a LEEDS certified office building. The building is aprox. 30000sf and its foundation is comprised of piles, pilecaps, and grade beams, aswell as a 13' high foundation wall below grade in the Lab portion of the building.
1) What are the structural and placement issues involved in incresing the amount of fly ash in the concrete mix.
2) What are the costs involved including unforseen hidden costs.
3) What overall inpact will incresing the fly ash content of the concrete have on the LEEDS point system. (Aprox. 1200 cu.yds of concrete. Aprox 4 million dollar building)
Thanks
Tourbillon
1) What are the structural and placement issues involved in incresing the amount of fly ash in the concrete mix.
2) What are the costs involved including unforseen hidden costs.
3) What overall inpact will incresing the fly ash content of the concrete have on the LEEDS point system. (Aprox. 1200 cu.yds of concrete. Aprox 4 million dollar building)
Thanks
Tourbillon