bridgebuster
Active member
- Jun 27, 1999
- 3,969
I'm working on a project that involves rehabilitating four 75-year old gravity walls; total length about 1700. Each wall varies in height from 4-feet to 26-feet (from top of footing).
A major portion of the work is replacing the parapets and curb at the top of the walls. The upper 2-feet of each wall is spalled because the dowels from the parapet into the stems only had about 1/2-inch cover.
The other aspect of the project is that we're removing 2-inches of concrete from the face of each wall and installing a new overlay - it'll be at least 5-inches thick. The community wants a very elaborate aesthetic treatment on the walls.
My question: Is there any known method to determine the spacing and depth of dowels to hold the overlay to the existing wall? We're using a hooked No. 4 bar every 15-inches horizontally & 24-inches vertically. This is based upon what I came across in some specs and guidelines for shotcrete. However, the wasn't any information on how deep the dowels should be. We're embedding the dowels 6-inches.
We came up with the 6-inch depth by crystal ball and averaging out the embeddment assuming the dowels were resisting the full lateral pressure of the wet concrete.
I've worked in the field on jobs where we attached jersey shaped parapets to existing vertical parapets. In looking at old drawings there was no consistent rebar pattern.
Any thoughts?
A major portion of the work is replacing the parapets and curb at the top of the walls. The upper 2-feet of each wall is spalled because the dowels from the parapet into the stems only had about 1/2-inch cover.
The other aspect of the project is that we're removing 2-inches of concrete from the face of each wall and installing a new overlay - it'll be at least 5-inches thick. The community wants a very elaborate aesthetic treatment on the walls.
My question: Is there any known method to determine the spacing and depth of dowels to hold the overlay to the existing wall? We're using a hooked No. 4 bar every 15-inches horizontally & 24-inches vertically. This is based upon what I came across in some specs and guidelines for shotcrete. However, the wasn't any information on how deep the dowels should be. We're embedding the dowels 6-inches.
We came up with the 6-inch depth by crystal ball and averaging out the embeddment assuming the dowels were resisting the full lateral pressure of the wet concrete.
I've worked in the field on jobs where we attached jersey shaped parapets to existing vertical parapets. In looking at old drawings there was no consistent rebar pattern.
Any thoughts?