Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Thrust Block Design 5

Status
Not open for further replies.

mtroche

Civil/Environmental
Jun 4, 2001
39
0
0
PR
I need information about the thrust block design procedure. In one side I have the momentum formula, and in the other side I have this formula T=2PAsin(phi) where “P” is the pressure, “A” is the pipe cross section area where the flow goes, and “phi” is the bend angle. Is the last formula a "rule of thumb" for the thrust block design? Using this formula, an engineer calculated 10 concrete trucks to build a thrust block for a 45 degrees, 48inches, vertical bend, and using the momentum formula I get only 2 concrete trucks for the vertical thrust block. The pressure (P) that he used was an assumed value equal to two times the working pressure for this pipeline. The working pressure for this pipeline is 150psi. So, at the end, the engineer is multiplying the working pressure by four!!

I know... I know. To design a Thrust Block I have to use the momentum formula and take in account the weight of the bend itself and the water inside the bend if it's a vertical thrust block, but I am a little confused with the engineer using that formula.

I'll be grateful if someone of you show me an example on how to design a vertical and horizontal thrust block.

Thank you for your information.
 
Replies continue below

Recommended for you

Suggest you check out the following reference: "Pipe Restraints: Design Fallacies" by Patrick J. Creegan, F. ASCE which appeared in the Journal of Transportation Engineering, Vol. 109, No. 6, November, 1983. This peer reviewed paper will give you clear definitive guidance and several worked examples.
 
better yet, do what most agencies are doing now, and eliminate the thrust block altogether. Restrain the joints! For a 48" pipe, this is a better idea. Sure, it's easier to just dump a bunch of "cement" in there - and a lot easier than installing those expensive mechanical joints, - but what a mess if you ever have to dig up those 10 truckloads of concrete.

Chuck
cgopperton@stantec.com
 
Status
Not open for further replies.
Back
Top