sheiko
Chemical
- May 7, 2007
- 422
Hello,
Working in an EPC company as a process engineer, i would like to know what are the key information a process engineer must provide to Piping Design in a Tie-In list and why?
I also would like to know the basic steps for planning, designing and constructing such Tie-In's in a Revamp project?
For example, i have found the following steps for Tie-In planning. Could you identify missing steps or additionnal one that you believe should be included?
1. Identify each Tie-In(s) schematic location on P&ID - Process Engineer
2. Review with Piping - Process & Piping Design
3. Create a Tie-In List with key information about each Tie-In -
Piping Design & Process Engineer
4. Review with Client - Process Engineer
5. Go to the Field to locate physical point of Tie-In - Piping
Design/Process
6. Meet with plant personnel and review Tie-In requirements -
Piping Design, Process, Plant Operations, Safety
7. Discuss different types and configurations of Tie-Ins - Piping
Design, Process and Plant personnel
8. Establish physical Tie-In location point and type - Piping
Design & Plant Personnel
9. Define if the line can be shut –down, when, how long, draining,
depressuring, steam-out and other safety issues - All personnel
10. Visually inspect the existing pipe. Are more extensive tests
needed to determine condition and suitability for the Tie-In -
Piping Design and Plant personnel
11. Mark or tag the selected Tie-In point - Piping Design & Plant Personnel
12. Photograph the Tie-In point - Piping Design
13. Draw sketch and take all required measurements - Piping Design
14. Determine locations of all existing block valves, vents and
drains - Piping Design
15. Determine the location of all existing anchors and guides -
Piping Design
16. Based on selected Tie-In location and type determine if
additional vents or drains will now be required - Piping Design,
Plant Operations
17. Include new vents or drains (if any) on sketch - Piping Design
18. Insure that this process is followed for all Tie-Ins - All participants
19. Get plant personnel to sign off on all data collected in the
field - Piping Design & Process Engineering
20. In the office modify the P&ID as required - Process Engineer
21. Convert all field sketches into appropriate production drawings
(Isometrics) - Piping Design
22. Prepare a Plot Plan style "Tie-In Location Key Plan"
23. Update the Tie-In List as required - Piping Design
24. Review all Tie-Ins with Pipe Stress for effect on existing
system piping and new system piping - Piping Design
25. Finalize (check, correct and approve) all Tie-In isometric
drawings - Piping Design
Please feel free to share any documentation you could. I have googled "piping tie in" but i did not find that much relevant information.
Thanks.
"We don't believe things because they are true, things are true because we believe them."
Working in an EPC company as a process engineer, i would like to know what are the key information a process engineer must provide to Piping Design in a Tie-In list and why?
I also would like to know the basic steps for planning, designing and constructing such Tie-In's in a Revamp project?
For example, i have found the following steps for Tie-In planning. Could you identify missing steps or additionnal one that you believe should be included?
1. Identify each Tie-In(s) schematic location on P&ID - Process Engineer
2. Review with Piping - Process & Piping Design
3. Create a Tie-In List with key information about each Tie-In -
Piping Design & Process Engineer
4. Review with Client - Process Engineer
5. Go to the Field to locate physical point of Tie-In - Piping
Design/Process
6. Meet with plant personnel and review Tie-In requirements -
Piping Design, Process, Plant Operations, Safety
7. Discuss different types and configurations of Tie-Ins - Piping
Design, Process and Plant personnel
8. Establish physical Tie-In location point and type - Piping
Design & Plant Personnel
9. Define if the line can be shut –down, when, how long, draining,
depressuring, steam-out and other safety issues - All personnel
10. Visually inspect the existing pipe. Are more extensive tests
needed to determine condition and suitability for the Tie-In -
Piping Design and Plant personnel
11. Mark or tag the selected Tie-In point - Piping Design & Plant Personnel
12. Photograph the Tie-In point - Piping Design
13. Draw sketch and take all required measurements - Piping Design
14. Determine locations of all existing block valves, vents and
drains - Piping Design
15. Determine the location of all existing anchors and guides -
Piping Design
16. Based on selected Tie-In location and type determine if
additional vents or drains will now be required - Piping Design,
Plant Operations
17. Include new vents or drains (if any) on sketch - Piping Design
18. Insure that this process is followed for all Tie-Ins - All participants
19. Get plant personnel to sign off on all data collected in the
field - Piping Design & Process Engineering
20. In the office modify the P&ID as required - Process Engineer
21. Convert all field sketches into appropriate production drawings
(Isometrics) - Piping Design
22. Prepare a Plot Plan style "Tie-In Location Key Plan"
23. Update the Tie-In List as required - Piping Design
24. Review all Tie-Ins with Pipe Stress for effect on existing
system piping and new system piping - Piping Design
25. Finalize (check, correct and approve) all Tie-In isometric
drawings - Piping Design
Please feel free to share any documentation you could. I have googled "piping tie in" but i did not find that much relevant information.
Thanks.
"We don't believe things because they are true, things are true because we believe them."