DenverJ
Civil/Environmental
- Jan 29, 2015
- 10
I wanted to know if this is an acceptable practice.
I have a small watershed (1.4 Ac) with a proposed gravel road in the middle. I am using a ditch turnout/level spreader to divert runoff from the roadside ditch to a forested area. I would like to run my Tc for the watershed from an upslope area down to the ditch, through the ditch, across the level spreader and through the forested area to my Point of Interest.
My question: Is it acceptable to enter the Tc as sheet flow below the level spreader?
I have a small watershed (1.4 Ac) with a proposed gravel road in the middle. I am using a ditch turnout/level spreader to divert runoff from the roadside ditch to a forested area. I would like to run my Tc for the watershed from an upslope area down to the ditch, through the ditch, across the level spreader and through the forested area to my Point of Interest.
My question: Is it acceptable to enter the Tc as sheet flow below the level spreader?