-
1
- #1
Cale237
Industrial
- Jan 15, 2021
- 1
Hello, I am not sure if this is the correct way to post. However, I need some help thinking through a time study at work. I am trying to create a standard for a work area. There is one machine. An operator loads carts onto a conveyor. The carts enter the machine in groups of 8. After machine is done with the cycle, the parts exit the machine on another conveyor. Then the operator unloads. If there are carts already inside the machine, the 8 carts entering must wait until the next cycle is completed. My main idea would be to track the time it takes the operator to load/unload and the machine/conveyor time, and I would stop the timer whenever the parts are not moving on the conveyor. What would be the best approach with this? I would think that a simulation software would give the best estimate since there is queuing involved on the conveyor, but I do not have that option. Any comments would be helpful. I am likely making this more complicated than it has to be.
Thank you
Thank you