amk7772005
Industrial
- Aug 30, 2005
- 1
Hi y'all,
I'm basically an entry-level engineer, and I've been thrown into time study work. I'm at a company who are trying to verify/update their standard piece rates, and are using time studies for that purpose.
I'm using the standard formula using Standard/Normal/Observed time with allowances and such. My allowances are set to 15%. I've also added in numerous extra elements, such as machine down time and restocking of parts, breaks/setups, and have included a rating factor for each operator in an effort to level out the times. A couple questions:
First, is the 15% allowance supposed to cover all extra elements such as machine down time and part stocking, or am I right to add that in seperately?
Second, I am getting a whole slew of results, from equal to the standard to 180% of the standard. I find it hard to believe that they're operating so far off their potential, and since I'm new at this I assume there's a flaw in my methods/analysis somewhere, but I can't figure out what that might be. I am confident on my measurements for the base elements, but am not sure I'm getting everything concerning the extra elements, although I've tried to be thorough.
Are there any tips or suggestions??? I am finding it impossible to find practical (or any, for that matter) literature on time studies. Any tips/advice would be most welcome. Thanks.
I'm basically an entry-level engineer, and I've been thrown into time study work. I'm at a company who are trying to verify/update their standard piece rates, and are using time studies for that purpose.
I'm using the standard formula using Standard/Normal/Observed time with allowances and such. My allowances are set to 15%. I've also added in numerous extra elements, such as machine down time and restocking of parts, breaks/setups, and have included a rating factor for each operator in an effort to level out the times. A couple questions:
First, is the 15% allowance supposed to cover all extra elements such as machine down time and part stocking, or am I right to add that in seperately?
Second, I am getting a whole slew of results, from equal to the standard to 180% of the standard. I find it hard to believe that they're operating so far off their potential, and since I'm new at this I assume there's a flaw in my methods/analysis somewhere, but I can't figure out what that might be. I am confident on my measurements for the base elements, but am not sure I'm getting everything concerning the extra elements, although I've tried to be thorough.
Are there any tips or suggestions??? I am finding it impossible to find practical (or any, for that matter) literature on time studies. Any tips/advice would be most welcome. Thanks.