Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

tips for heat treatment of A312 S31050

Status
Not open for further replies.

abramb

Mechanical
May 19, 2009
18
Good morning to all, I'm abramb.

About heat treatment of ASTM A312 S31050, where can I find more information about heat treatment parameters for this material?
Do you have any experience about this material?

Thanks in advance,
A.
 
Replies continue below

Recommended for you

(note: 310MoLN) This alloy needs to be handled like a 6%Mo in order to get the best performance.
What is the thermo-mechanical history of the pieces that you will be heat treating? Formed? welded?
If welded you will need high temps and long hold times to get good homogenization. Reasonably fast cooling also, but this isn't hard with tubulars.
I would look to use temps of 2050F-2100F and hold times of at least 10 min at temp followed with a forced cooling.

= = = = = = = = = = = = = = = = = = = =
Plymouth Tube
 
Thank you EdStainless for you answer.

The source material is a forged ingot, then we can have two different thermo-mechanical histories:

1. tubular products: machining, heat treatment, final machining
2. other products: hot forming, heat treatment, final machining

just another question about hold times:
you mean 10 min total, is it not depending by the wall thickness of the piece?
What about setting the hold time 2 min for each mm of WT, keeping 10 min minimum for small WT? Would it be ok?


A.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor