Good afternoon to all,
i have a question for you. During maintanace operations of a tank, it's necessary to open a temporary door in the 1° shell course.
After 2 months that door was welded and regularly checked with RT and MT with with no defect, some toe cold cracking appeared in the horizontal seam at 2/3 mm of depth (tk plate 45mm).
What could be the causes of such defects?
Thank you