Jmeng1026
Structural
- Jun 11, 2018
- 57
I am working on a set of plans for a five unit townhouse building that had a fire and now needs to make some upgrades to meet code.
The units are two stories and there is a double wood stud wall separating each unit. However, the floor joists bear on the double wood stud wall and overlap each other.
Typically two layers of 5/8" type x gypsum is installed on both sides of the wall from slab to roof sheathing (with a gable truss on each side of the wall). However, in this case the floor joists are creating a problem.
The only thing I can think of is to put the double layer of gypsum on the 1st floor wall, then get the 1st floor ceiling to be fire rated and then put a double layer of gypsum on the 2nd floor wall up to the roof sheathing. Would that work?
Is there a way to do it without having to fire rate the ceiling?
Thank you for the help.
The units are two stories and there is a double wood stud wall separating each unit. However, the floor joists bear on the double wood stud wall and overlap each other.
Typically two layers of 5/8" type x gypsum is installed on both sides of the wall from slab to roof sheathing (with a gable truss on each side of the wall). However, in this case the floor joists are creating a problem.
The only thing I can think of is to put the double layer of gypsum on the 1st floor wall, then get the 1st floor ceiling to be fire rated and then put a double layer of gypsum on the 2nd floor wall up to the roof sheathing. Would that work?
Is there a way to do it without having to fire rate the ceiling?
Thank you for the help.