RRaghunath
Electrical
- Aug 19, 2002
- 1,716
Transmission systems face Over voltage issues during grid disturbances when there is loss of major loads, leaving a large no. of unloaded or lightly loaded lines in the system (with associated excess VARs).
How do utilities control the situation? Is tripping of identified transmission lines an option followed by any utilities and if so, is the tripping logic based on OV+<MW+>MVAR??
Appreciate sharing any experiences. Thanks
How do utilities control the situation? Is tripping of identified transmission lines an option followed by any utilities and if so, is the tripping logic based on OV+<MW+>MVAR??
Appreciate sharing any experiences. Thanks