JAS
Mechanical
- Nov 9, 2014
- 28
Dear All,
Will there be any issue of transporting a 50m PV on road by trailer on road, assuming that we have got clearance from the Transport Authority & Vendor designs for the same with transport saddle.
After that, how this will be transported within the refinery plant.
We need to transport this as well as need to prepare a constructability report for the same.
It may be challenging to transport a 50m lengthy vessel in the presence of other running equipments in the plant.
I request you to throw some light on the same.
Thanks,
JAS
Will there be any issue of transporting a 50m PV on road by trailer on road, assuming that we have got clearance from the Transport Authority & Vendor designs for the same with transport saddle.
After that, how this will be transported within the refinery plant.
We need to transport this as well as need to prepare a constructability report for the same.
It may be challenging to transport a 50m lengthy vessel in the presence of other running equipments in the plant.
I request you to throw some light on the same.
Thanks,
JAS