I am designig the electrical installation of a Gas Compression Plant, and I decided to run 13.8 KV, 4.16 KV and 480 Volts cables, in sand trenches with concrete covers. But the client wants concrete duct banks. I am compiling my arguments to defend my sand trenches decision and I can mention:
- Quicker installation.
- Lesser cost.
- Better cooling or temperature behaviour.
The client says that cables replacement or future cables installation in sand trenches is more complicated than in duct banks.
Some arguments to defend (or to discard) the decision will be appreciated.
Regards
- Quicker installation.
- Lesser cost.
- Better cooling or temperature behaviour.
The client says that cables replacement or future cables installation in sand trenches is more complicated than in duct banks.
Some arguments to defend (or to discard) the decision will be appreciated.