In case of turbocompressor trains (API617), I would ask for your insight to clarify the following :
1 - Single Source : Is this mean that Each equipment, Gas Turbine and Compressor, are both provided from the same Manufacturer. This leads Ipso Facto to Single Responsability.
2 - Not Single Source : In this case, Gas Turbine and Compressor shall be provided from different Manufacturer.
Train Responsability in case of Not Single Source supply : Shall one of the Manufacurer (compressor or Gas Turbine) always buy the other part of equipment from the other manufacturer and then take full train
responsability in face of the end user. Or do you forseen alternative scenario ?
So as per API, who has the train responsability? is it the compressor or the Gas Turbine Manufacturer? And eventually, how this is related to String test if it is performed?
Any reference to API codes/paragraph would be appreciated
Thanks in advance
Regards
Wimple
In case of turbocompressor trains (API617), I would ask for your insight to clarify the following :
1 - Single Source : Is this mean that Each equipment, Gas Turbine and Compressor, are both provided from the same Manufacturer. This leads Ipso Facto to Single Responsability.
2 - Not Single Source : In this case, Gas Turbine and Compressor shall be provided from different Manufacturer.
Train Responsability in case of Not Single Source supply : Shall one of the Manufacurer (compressor or Gas Turbine) always buy the other part of equipment from the other manufacturer and then take full train
responsability in face of the end user. Or do you forseen alternative scenario ?
So as per API, who has the train responsability? is it the compressor or the Gas Turbine Manufacturer? And eventually, how this is related to String test if it is performed?
Any reference to API codes/paragraph would be appreciated