ClemsonVet
Civil/Environmental
- May 12, 2016
- 31
I have a rail spur on a project that is in Norfolk Southern's jurisdiction and they require HDPE in their black design manual. I don't use HPDE in large diameter often. I'm reaching out to see if anyone knows of a concrete headwall detail for this scenario? I would prefer using a double concrete headwall as attached but how would the HPDE be connected to the headwall Properly? this detail shows CMP or RCP.
thanks in advance.. let me know if this is in the wrong forum section.
D
thanks in advance.. let me know if this is in the wrong forum section.
D