Awilcox1821
Mechanical
- Apr 3, 2011
- 4
thread256-54204
Hi,
I have read the post referenced above, all great information I still have a few questions.
1) should I include rebar in the new pour? To tie each successive section together?
2) The existing wall is poured concrete with a stone footing-if you want to call it that!, the wall is 10" thick, if I dig out a 2' long section of dirt, to the required depth, would it be sufficient to have an overall finished footing 16" in thickness/depth underneath the 10" thick/deep wall?
3) the soil is very very stiff clay, if I do not disturb the soil at the bottom of the pit do I need gravel or sand? Or can I just pour onto the dirt?
4)lf cost isn't an issue can I use a non shrink grout? If so how big should the gap be between the new and old footing?
Many thanks Anthony
Hi,
I have read the post referenced above, all great information I still have a few questions.
1) should I include rebar in the new pour? To tie each successive section together?
2) The existing wall is poured concrete with a stone footing-if you want to call it that!, the wall is 10" thick, if I dig out a 2' long section of dirt, to the required depth, would it be sufficient to have an overall finished footing 16" in thickness/depth underneath the 10" thick/deep wall?
3) the soil is very very stiff clay, if I do not disturb the soil at the bottom of the pit do I need gravel or sand? Or can I just pour onto the dirt?
4)lf cost isn't an issue can I use a non shrink grout? If so how big should the gap be between the new and old footing?
Many thanks Anthony