khu
Civil/Environmental
- Aug 8, 2019
- 25
I need some help understanding the minimum 2 ft/s "self-cleaning" velocity referenced by the 10-state and many other standard documents. I've read the other posts on this subject, but my specific question was never quite answered that I could find.
"All sewers shall be designed and constructed to give mean
velocities, when flowing full, of not less than 2.0 feet per second
(0.6 m/s), based on Manning's formula using an "n" value of 0.013."
I've always taken this to mean that at my design flow, I need to have a minimum velocity of 2 ft/s in the pipe. However, the line "when flowing full (half full included in some documents)" has me a little confused. My issue is that on a development that I'm involved with, my design flows for the first phase are producing less than 2 ft/s. When the second phase comes online, I'm meeting the 2 ft/s requirements for my actual calculated flows. For the first phase though, I would need some of these pipes over 3% to meet the 2 ft/s at my design flows, which is going to cause a very deep pipe at my wet well 1000' away.
I'm just confused why the 10-state indicates that the 2 ft/s requirement is when the pipe is flowing full (or half by some standards). My pipes do meet that criterion, but they will never actually flow half full. Even with Phase 2 flows coming in, my max d/D is only 0.3 in an 8" pipe. Do I design my slopes to meet 2 ft/s at my design flow or 2 ft/s flowing full/half full?
"All sewers shall be designed and constructed to give mean
velocities, when flowing full, of not less than 2.0 feet per second
(0.6 m/s), based on Manning's formula using an "n" value of 0.013."
I've always taken this to mean that at my design flow, I need to have a minimum velocity of 2 ft/s in the pipe. However, the line "when flowing full (half full included in some documents)" has me a little confused. My issue is that on a development that I'm involved with, my design flows for the first phase are producing less than 2 ft/s. When the second phase comes online, I'm meeting the 2 ft/s requirements for my actual calculated flows. For the first phase though, I would need some of these pipes over 3% to meet the 2 ft/s at my design flows, which is going to cause a very deep pipe at my wet well 1000' away.
I'm just confused why the 10-state indicates that the 2 ft/s requirement is when the pipe is flowing full (or half by some standards). My pipes do meet that criterion, but they will never actually flow half full. Even with Phase 2 flows coming in, my max d/D is only 0.3 in an 8" pipe. Do I design my slopes to meet 2 ft/s at my design flow or 2 ft/s flowing full/half full?