AK92
Geotechnical
- Aug 20, 2013
- 45
Hi all,
For some reason, the client is unwilling to use cohesionless backfill for a temporary reinforced earth wall (using wraparounds) for the edge of an embankment fill. So far, they are proposing the use of MH type soils. I'm concerned about the problems that using cohesive fill might cause as they are generally not recommended for reinforced earth applications. Are there any design manuals to cope with designing reinforced earth walls with cohesive backfill?
The general ideas I'm thinking of is using a combination of
1) placing the fill wet of optimum, then allowing for the consolidation settlements
2) using nonwoven geotextiles (for drainage and dissipation of excess pore pressures to improve bond strength and reduce water pressure) and geogrids (to provide the tensile strength).
I'm not too concerned about the deformation as it is for a temporary fill. The ground beneath the embankment would be laced by wick drains allowing the whole fill to settle, and then the surcharge fill would be taken off. The reason why the temporary reinforced earth wall has to be there is due to a lack of space. So in essence, the temporary reinforced earth wall would have to be designed to settle along with the ground.
For some reason, the client is unwilling to use cohesionless backfill for a temporary reinforced earth wall (using wraparounds) for the edge of an embankment fill. So far, they are proposing the use of MH type soils. I'm concerned about the problems that using cohesive fill might cause as they are generally not recommended for reinforced earth applications. Are there any design manuals to cope with designing reinforced earth walls with cohesive backfill?
The general ideas I'm thinking of is using a combination of
1) placing the fill wet of optimum, then allowing for the consolidation settlements
2) using nonwoven geotextiles (for drainage and dissipation of excess pore pressures to improve bond strength and reduce water pressure) and geogrids (to provide the tensile strength).
I'm not too concerned about the deformation as it is for a temporary fill. The ground beneath the embankment would be laced by wick drains allowing the whole fill to settle, and then the surcharge fill would be taken off. The reason why the temporary reinforced earth wall has to be there is due to a lack of space. So in essence, the temporary reinforced earth wall would have to be designed to settle along with the ground.