jjezmarlo3
Structural
- Aug 9, 2012
- 13
How have all of you concrete tank designers out there been modifying the tables in PCA's Rectangular Concrete Tank publication when the operating water surface is well above the top of the tank wall (i.e. significant freeboard)? Do you just assume that the top of the concrete tank is down at the operable water level, or do you modify the tables somehow? I would appreciate your insight.