cyphos168
Civil/Environmental
- Feb 25, 2016
- 37
Hi,
What's the general rule about using short piles for the foundation of tall building? The thing is the ground is neither good nor bad. 250mm square concrete piles only penetrated around 7m into the ground. With pile cap in place we are only looking at around 4.5m pile remaining in the ground supporting the structure. This is no longer so much a friction pile but rather end bearing pile.
Is it ok to use short piles or would I be better off switching to bored pile instead? Assuming over excavation of the ground does not happen and the piles remain in place. How about bearing capacity failure and heaving of the ground? Thanks.
Alex
What's the general rule about using short piles for the foundation of tall building? The thing is the ground is neither good nor bad. 250mm square concrete piles only penetrated around 7m into the ground. With pile cap in place we are only looking at around 4.5m pile remaining in the ground supporting the structure. This is no longer so much a friction pile but rather end bearing pile.
Is it ok to use short piles or would I be better off switching to bored pile instead? Assuming over excavation of the ground does not happen and the piles remain in place. How about bearing capacity failure and heaving of the ground? Thanks.
Alex