It is usual to specify the general sort of conditions that trigger force majeure clauses; war, riots, etc are the common ones.
You may put in shortage of labour but I think that that would be a tough one to prove or disprove since there are always people available if you are willing to pay enough money.
If you can pay enough money to avoid the impact of the event or circumstances than that is not a force majeure type of condition.
What trade are we talking about here? You can always put an advertisement in the St John newspaper.
You have two options that I see. One is to grant the contractor extra time or money to complete the work and the other is to stick him to the exact letter of the contract and make him responsible for the time and or money cost.
What is your end goal here? Is it to enforce the letter of the contract at all costs or is to get your project complete and productive on time?
If it is to enforce the contract at all costs then deny any claim and generally stick the contractor with the problem. This may delay your completion because is the contractor goes bankrupt you will have to re-tender and start again. It may affect other work to come later exposing you to delay claims on these jobs. You may get some financial relief from any bonds or insurance in place but once these run out and the contractor is bankrupt then you will be on the hook for all costs.
I also doubt if lost revenue or potential profits are a factor to be considered in fighting a delay claim either.
You will also get a reputation as someone who put a local contractor out of business and when you have a small job you will have a smaller pool of contractors willing, available and capable of doing your work.
If your goal is to get the job done on time then sit down with the contractor and openly and honestly discuss how you can achieve that. You may have to pay extra but this may be much less than the costs of delaying the work.
You will gain a contractor locally who is willing to work with you in the future even to the point of giving you preferential treatment (emergency response for example).
I once worked for a pulp and paper mill. We were replacing the debarking equipment. The debarking of the logs is the first step and if the debarking stops then the supply of logs for the process stops and no paper is coming out the other end of the mill in addition to shut down and other costs.
We were told at the start of the job that the mill made $1,000,000 a day and we were to do nothing to screw that up. The mill followed through by treating their contractors very well. They were virtually guaranteed of making a fair profit unless they did something really stupid. They would respond very quickly to all of our concerns and if something came up that was not considered at the bid time then we sat down and discussed it. If extra cash was required to fix the problem it was available.
The end result was that we could get any of the contractor we to do almost anything we wanted or needed them to do. If one contractor was short of equipment because of a breakdown the equipment was supplied by another, often the competitor, with no hassle.
We paid out several thousand in extras that were arguably the contractor’s responsibility. However this was money well spent because we could have spent more than that arguing about the issues and negated the considerable good will between the mill and the contractors and delayed the project.
We removed all the debarking equipment and replaced it with new including the waste disposal equipment on time with no unscheduled shutdowns of the plant and continued to process between 700 and 800 cords of wood a day.
My point is that sticking the contractor to the letter of the contract may be the most costly decision you can make. Give and take is required on all construction projects and this sounds like one of those cases.
Rick Kitson MBA P.Eng
Construction Project Management
From conception to completion