Actually, the inclusion of "shortages of necessary labour" as a valid clause to declare Force Majeur is going the other way - we are sharing the risk. We are recognizing that labout shortage may be a problem, and thereby allowing the contractor to declare FM, thereby allowing for relief from costs, penalties and schedule.
If there is no clause to declare FM, then the contractor is subject to the penalties incurred as a result of a shortage of necessary labour.
is it common to for "shortages of necessary labour" to be included as a valid cause to declare Force Majeur?
RDK said:I get back to the question of what is the main objective.
RDK said:What is your objective? To pin the alligator in a wrestling match or drain the swamp?