Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations pierreick on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Valley & Hip Conditions for Wood Framed Cathedral Ceiling

Status
Not open for further replies.

smb4050

Structural
Jul 19, 2006
89
There have been several posts about design of wood framed cathedral ceilings using a ridge beam for gravity loads, but what about the connections and horizontal loads for cathedral ceilings with valley and hip conditions? Should a connection between 2 joists at a valley or hip still have a tension strap? Does diagraph action resolve these loads?
What if a ridge beam ends at hip condition without a support column? Is a tension member (collar beam) required? Just wondering how other engineers address these conditions. Thanks
 
Replies continue below

Recommended for you

Should a connection between 2 joists at a valley or hip still have a tension strap? Does diagraph action resolve these loads?

No and yes.

What if a ridge beam ends at hip condition without a support column? Is a tension member (collar beam) required?

Not necessarily required, if a moment connection can be provided.