JAE
Structural
- Jun 27, 2000
- 15,576
I've got a small building addition - which is really just a two story set of stairs and an elevator/lobby. We set the whole thing on an 18" mat foundation over the entire footprint.
I understand about slab curling and generally have the vapor barrier issues figured out.
But with an 18" thick foundation mat, that is also to serve as the lower floor slab, the question has come up as to whether a vapor barrier under the 18" mat is required.
Normally, with a 4" to 8" slab, I would not use a VB if the slab was to serve as an exposed concrete floor as curling, cracking, etc. is helped a bit by not having a VB underneath.
And where there is carpet, tile, etc. I would use a VB for helping in long term control of moisture from below.
But this 18" mat will have vinyld tile applied to the top surface so I'm sensitive to vapor pressure coming up from below.
Would it make sense to not use a VB underneath (thinking that it would impair good curing through the mat thickness) and then notify the architect that special care, or tests, would be required prior to placing any tile on the concrete? The tests would check for vapor pressure. Might require a longer wait prior to placing tile but that's all I can think of.
I understand about slab curling and generally have the vapor barrier issues figured out.
But with an 18" thick foundation mat, that is also to serve as the lower floor slab, the question has come up as to whether a vapor barrier under the 18" mat is required.
Normally, with a 4" to 8" slab, I would not use a VB if the slab was to serve as an exposed concrete floor as curling, cracking, etc. is helped a bit by not having a VB underneath.
And where there is carpet, tile, etc. I would use a VB for helping in long term control of moisture from below.
But this 18" mat will have vinyld tile applied to the top surface so I'm sensitive to vapor pressure coming up from below.
Would it make sense to not use a VB underneath (thinking that it would impair good curing through the mat thickness) and then notify the architect that special care, or tests, would be required prior to placing any tile on the concrete? The tests would check for vapor pressure. Might require a longer wait prior to placing tile but that's all I can think of.