Hi,
I am working on project in Canada where we are constructing a large concrete tank on grade. The contractor allowed the subgrade to freeze after preparing the subgrade and placing a protective mudslab. Once the reinforcement for the structural base slab is installed, they plan to heat and hoard the slab for a period of 3-4 days to remove the frost from the beneath the slab. I am wondering what the contractor to do to verify the subgrade has been heated sufficiently that the frost has been completely removed.
I am working on project in Canada where we are constructing a large concrete tank on grade. The contractor allowed the subgrade to freeze after preparing the subgrade and placing a protective mudslab. Once the reinforcement for the structural base slab is installed, they plan to heat and hoard the slab for a period of 3-4 days to remove the frost from the beneath the slab. I am wondering what the contractor to do to verify the subgrade has been heated sufficiently that the frost has been completely removed.