Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Vessel field pneumatic testing with piping together 1

Status
Not open for further replies.

jtseng123

Mechanical
Jun 6, 2012
530
Dear,

We have vessels with welded nozzles for LNG service. Shop has done hydrotested per UG-99(b)and code stamped. Field already welded all pipes to the nozzles and will go through pneumatic testing the entire system since isolation of the piping is not possible. For sure any pre-caution will be taken and follow very strict safety procedures. The question is, can we air pressurize to the original water test pressure per UG-99(b)? or we have to use reduced pressure per UG-100 (1.1x MAWP x stress ratio) ? Will the mechanical warranty be voided ?

 
Replies continue below

Recommended for you

As I understand it you are testing piping attachment welds that are welded to nozzles on the vessel. I agree with David that these welds are outside the scope of Section VIII. These welds should be tested in accordance with the Code for the piping (if any)and can be done at a reduced pressure. I would recommend the following.

1. Determine what if any piping code should be followed
2. If none perform volumetric examination of the weld.
3. Perform a low pressure leak test, such as a halogen test.
4. I would Article 10 of section V as a guide.

Hope this helps
Allan
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor