altoid3000
Mechanical
- Aug 29, 2004
- 21
On a tower there is a 14" feed nozzle in the cone section. The pipe runs all the way down to the bottom. About 60 feet. Now, the flow is 2 phase and the pipe is going to be vibrating. What precautions do I need to take , what analyses do I need to make to properly secure the pipe to the vessel? The pipe support clip will have fatigue loading and I want to properly design it. If we provide a proper anchor at the bottom, will that solve the problem ? Please direct me to some good reading about this problem.