tpd67
Civil/Environmental
- Oct 31, 2006
- 2
I'm trying to fully understand the cause of Warning Message 79 (HydroCADD Version 6.10). I received the following message:
"[79] Warning: Pond M020 Submerged Pond M019 Primary device #1 OUTLET by 0.37'"
This is a closed drainage system. Ponds M020 and M019 are manholes connected by a 12" RCP. As I understand the message, conditions in Pond M020 result in the peak elevation being 0.37' (4.44") above the RCP invert at Pond M019. This means the pipe is about 1/3 full at the peak flow.
Am I interpreting this correctly? What's the problem with this situation?
"[79] Warning: Pond M020 Submerged Pond M019 Primary device #1 OUTLET by 0.37'"
This is a closed drainage system. Ponds M020 and M019 are manholes connected by a 12" RCP. As I understand the message, conditions in Pond M020 result in the peak elevation being 0.37' (4.44") above the RCP invert at Pond M019. This means the pipe is about 1/3 full at the peak flow.
Am I interpreting this correctly? What's the problem with this situation?