We have two pieces of equipment that requires process water in a new building. One requires 60 gpm @ 70 psi and the other requires 50 gpm @ 65 psi and will operate concurrently. We want to advise the owner of the total flow/pressure required coming into the building. Is this simply the combined flow at the higher pressure? So 110 gpm @ 70 psi? This is just a proposal stage, so just trying to advise the client on what they will need to supply for water. Don't require a bunch of analysis at this point. Thanks