moltenmetal
Chemical
- Jun 5, 2003
- 5,504
We're considering a thermosiphon reboiler, carbon steel construction with an electric element, providing saturated steam at 260-300 C to a coil in a pilot plant process vessel.
The water/steam system is totally closed, and will only be opened if leakage has depleted the water sufficiently. There are very few joints in the system so it shouldn't be opened often.
Any recommendations on a passivation procedure prior to protracted operation? Any recommendations for water preparation? Don't direct us to Nalco or the like, because they're not anxious to bother answering questions like this if there's no ongoing need for chemicals.
The water/steam system is totally closed, and will only be opened if leakage has depleted the water sufficiently. There are very few joints in the system so it shouldn't be opened often.
Any recommendations on a passivation procedure prior to protracted operation? Any recommendations for water preparation? Don't direct us to Nalco or the like, because they're not anxious to bother answering questions like this if there's no ongoing need for chemicals.