hrdrok
Mining
- Jan 11, 2010
- 4
Simple,
I need to move ~10,000 usgpm of water over 3000 feet, in subartic conditions, 24/7 run conditions.
Negligible head (10m +/-) plus line loss.
Heat trace and insulated pipe not an option due to cost.
Anybody have a minimum flow velocity to prevent line freezing,
Probably sclair DR17, water at low single digits (C). Ambient air temp -20C and warmer.
ANy ideas?
I'll put this in civil as well.
h_r
I need to move ~10,000 usgpm of water over 3000 feet, in subartic conditions, 24/7 run conditions.
Negligible head (10m +/-) plus line loss.
Heat trace and insulated pipe not an option due to cost.
Anybody have a minimum flow velocity to prevent line freezing,
Probably sclair DR17, water at low single digits (C). Ambient air temp -20C and warmer.
ANy ideas?
I'll put this in civil as well.
h_r