Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Weld Analysis for support hitch

Status
Not open for further replies.

bricklayer

Mechanical
Feb 25, 2009
8
US
As shown in the attachment I have a hitch which will be welded to a 1/2” plate. The max force the hitch would see is 1500Lbf. The position of the force will induce a bending moment. I have been going though my Shigley’s book and the attached calculation is what I have come up with. I am really unsure if it is even close to being correct. So I was looking for some feed back as to if I am on the right path or not. The hitch is to have a 1/4” fillet weld around the base. So I calculated the moment of inertia of the weld using the line method as described in Shigley’s. My first question is do I need to rotate my bending stress element using a Mohr’s circle like I did prior to adding it to my stress caused by the tension force or do I just add the two and do a Mohr’s circle only once? My next question pertains to the base material. I know the allowable is 0.4 * the yield strength of the material but what area do I use, can I use the full leg of the weld or do I use the throat? And then what force do I use, do I do a P/A+MC/I? I have asked these questions to some of the guys I work with but they always use some rule of thumb fillet size and never question it, where as I want to fully understand it. Any help is greatly appreciated. Thanks in advanced.
 
Replies continue below

Recommended for you

Hi bricklayer

I used the "treat weld as a line" method from Machine Design by Schaum's Outline series.
I am not sure why you are doing Moh'r stress circles?
Anyway I have attached a file of how I would do your problem.

regards

desertfox
 
 http://files.engineering.com/getfile.aspx?folder=615149fe-371a-49ef-8bb0-6b81b201b389&file=weld_stress_calcs.pdf
desertfox,

Thanks for the response; I like your methodology it’s simple and easy to understand. When I get into the office tomorrow I will give it a shot.

The use of the Mohr’s circle came from my Shigley’s book. From what I understand it assumes that the weld should fail in shear, along the throat plane. Therefore you calculate your stresses and put them into a Mohr’s circle to get your max shear stress. Then you compare that to 0.3 * Su (Ultimate Strength) of the filler material. I got the allowable (0.3*Su) from some AWS standard.

Have you or anyone ever seen a weld calculation done this way?

Thanks

Bricklayer
 
I'd check (double-check ?) your assumptions of a load.

You're using 1500 lbs as a load on a "hitch" - as if it were a trailer or towing (pulling) point.

Are you comfortable with that (maximum) load - a steady pull on a known load (like a come-along or chain fall) is (somewhat) predictable - as long as the mechanic obeys your posted load limit sign at least.

(A library shelf would be predictable too - until somebody climbs the shelf to put a book away on the top.....)

But a trailer hitch on the road or shop conditions should allow for "g" forces from shock and bounce - even unexpected ones like hitting a curb or hole that might easily triple your "normal" tongue and pulling weight.
 
racookpe1978,

That 1500 lbs load is the load considering "g" forces and shock.

Thanks

Bricklayer
 
Not to muddy the water, but I spend half my time thinking about what I'm welding to.
If its a 2.5 inch square tube then the ~1.25 inch long welds inline with the top and bottom sides of the tube are the only ones capable of transferring much of the load.

I suspect the gusset that appears here above the receiver resulted partly from that concern.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top