HereTwoLearn
Structural
- Dec 20, 2009
- 9
Question 1: What is the best approach to weld inspection for T Y & K connections (pipe to pipe fishmouth welds)? (For example: Maybe the prepared connection gets visually inspected prior to welding, and then the root pass gets magnetic particled, and then the fill and cap passes get ultrasonic tested)
Question 2: If the welds were all completed, and you wanted them inspected, what methods would you suggest?
(The welds are either CJP or PJP per AWS D1.1. The application is a typical, static, structure.)
Thanks for your opinion and input.
Question 2: If the welds were all completed, and you wanted them inspected, what methods would you suggest?
(The welds are either CJP or PJP per AWS D1.1. The application is a typical, static, structure.)
Thanks for your opinion and input.